Delay in Providing Information

The Contracting Entity may drag on providing the necessary information, materials, approvals, remarks, essential for contract execution.

The Contracting Entity is obligated to post all required procurement documentation on the Public Procurements Portal before determining the winner.

Responsible institutions

Internal Government Audit Committee of the Ministry of Finance of the Republic of Kazakhstan (IGAC)

Oversight of Compliance with the Republic of Kazakhstan’s Procurement Legislation, including Desk Audits

010000, Nur-Sultan city, Zhenis Avenue, 11.

gov.kz/memleket/entities/kvga/about/structure/departments/leadership/1188/1?lang=ru

Regional Internal Audit Departments of the Republic of Kazakhstan (RIADs) 

Territorial Divisions of the Internal Government Audit Committee of the Ministry of Finance of the Republic of Kazakhstan

Conducting Scheduled On-Site Audits

010000, Nur-Sultan city, Zhenis Ave, 11.

gov.kz/memleket/entities/kvga/about/structure/100/1?lang=ru

Office of the Attorney General

010000, Nur-Sultan, Mangilik El Avenue, 14.

gov.kz/memleket/entities/prokuror/contacts?lang=ru

Anti-Corruption Agency of the Republic of Kazakhstan

Prevention, detection, suppression, disclosure, and investigation of economic and financial offenses.

010000, Nur-Sultan city, S. Seifullin street, 37.

gov.kz/memleket/entities/anticorruption/contacts?lang=ru

Dispute Templates

General Risk Template

Purchasing examples

The Contracting Entity provided a meal schedule two months after the contract was signed.

"Practically for two months, I organized meals without a schedule.
The real horror dawned on me when I eventually saw it. According to the schedule, meals were supposed to be provided daily. Understandably, this drastically deteriorated and fundamentally changed the contract terms. For us, it wasn’t just unprofitable, it was insurmountable," said the entrepreneur.